Contract Award

Project Award for the four projects currently comprising the Stettler Rural Water Servicing Strategy are listed in the table below.

Project   Company
South Endiang Water System   Gendre Construction
North Endiang Water System   NuEdge Construction Ltd.
North Byemoor Water System   Gendre Construction Ltd.
South Byemoor Water System   NuEdge Construction Ltd.

 

South Byemoor Water System Preliminary Tender Results

Company Total Contract Price (Including GST)
Gendre Construction Inc. $1,196,506.50
NuEdge Construction Ltd. $1,219,751.61
Corvet Construction $1,352,499.12
Wally's Backhoe Services Ltd. $1,372,555.80
Skocdopole Construction $1,396,273.20
Chinook Pipeline $1,522,225.90
Kennedy Oilfield Services Ltd. $1,600,068.75
Watson Welding Ltd. $1,607,248.02

The experience and references scores will be included in the decision for final Tender Award as per the tender process included in the Tender Documents. The Table above does not necessarily reflect the upcoming Tender Award and final Tender Scoring.

North Byemoor Water System Preliminary Tender Results

Company Total Contract Price (Including GST)
Gendre Construction Ltd. $850,360.35
NuEdge Construction Ltd. $927,871.56
Wally's Backhoe $949,103.40
Skocdopole Construction $985,841.85
Chinook Pipeline Inc. $1,022,424.85
Corvet Construction Ltd. $1,049,344.17
Watson Welding Ltd. $1,076,760.72

The experience and references scores will be included in the decision for final Tender Award as per the tender process included in the Tender Documents. The Table above does not necessarily reflect the upcoming Tender Award and final Tender Scoring.

North Endiang Water System Preliminary Tender Results

Company Total Contract Price (Including GST)
NuEdge Construction Ltd. $1,170,804.39
Gendre Construction $1,253,334.60
Skocdopole Construction Ltd. $1,373,573.25
Chinook Pipeline Inc. $1,422,722.23

The experience and references scores will be included in the decision for final Tender Award as per the tender process included in the Tender Documents. The Table above does not necessarily reflect the upcoming Tender Award and final Tender Scoring.

South Endiang Water System Preliminary Tender Results

Company Total Contract Price (Including GST)
Gendre Construction $1,384,179.30
NuEdge Construction Ltd. $1,439,295.90
Chinook Pipeline Inc. $1,592,700.90
BYZ Construction $1,763,007.75
Laforce Construction $2,909,104.80

The experience and references scores will be included in the decision for final Tender Award as per the tender process included in the Tender Documents. The Table above does not necessarily reflect the upcoming Tender Award and final Tender Scoring.

Tender Documents

Four projects for the Stettler Rural Water Servicing Strategy were released for tender on February 17, 2010. The documents are available at the Stantec Red Deer Office and through the Red Deer Construction Association, as well as from the links below. The tenders will be received in accordance with the following schedule:

South Endiang Water Servicing - Wednesday March 3, 2010 at 2:00 PM - Stettler County Office

North Endiang Water Servicing - Friday March 5, 2010 at 2:00 PM - Stettler County Office

North Byemoor Water Servicing - Wednesday March 10, 2010 at 2:00 PM - Stettler County Office

South Byemoor Water Servicing - Friday March 12, 2010 at 2:00 PM - Stettler County Office

To be included on the document holders list for notification of addendum, please contact Stantec Consulting Ltd. - 403-341-3320

The Plan

The County of Stettler has developed a Rural Water Servicing Master Plan with the goal of providing all landowners the opportunity to receive a safe, assured supply of potable water for household use.

Council knows water is critical not only to every farm, but is vital to the well being and long term sustainability of the County, hamlets and the Villages. Even in areas where there is adequate well water, there are still risks of contamination, diminished quality and reduced supply.

County Council, together with your MLA and MP, has secured grants from the Building Canada Fund in the amount of $6M to allow the construction of Phase One of the rural water system this fall. This funding, coupled with the current investments in the Starland-Stettler and Shirley McClellan regional water systems, enables the County to move forward with the Rural Water Servicing Master Plan. By leveraging these opportunities the County is able to assure water supply to landowners and create opportunities for growth within our County at a reasonable cost.